Augers MCC and Installation

Scope of Works:

  • Build and Supply of 2 new 400 Amp MSB and MCC panels to control all new Screw conveyors

  • Disconnection and marking of all redundant and reused circuits to allow for new equipment to be relocated

  • Reconnection and commissioning of all equipment for the render area

  • Upgrade of Estop system and interlocking with stand alone machines

  • All field wiring and testing along with startup support all within 10 days

Man hours: 1700

Lost time: 0